Click here to read the latest construction update for February, 27, 2018

  • Installed storefront and celestial window frames
  • Began to stucco the pitched high roof soffit at the main entrance
  • Began to lathe the flat high roof soffit at the northeast over the bank
  • Installed ductwork in the office areas