Click here to read the latest construction update for March 20, 2018
- Installed dining room windows and began kiosk framing
- Installed bathroom wall tile next to the dining room
- Began painting the south side of the mall in the sponsor areas
- Began stucco on the sides of the high pitched roof over the dining room and started removing scaffolding